Reopening section of Newport’s Cliff Walk delayed

Newport Cliff Walk

NEWPORT, R.I. (AP/WPRI) — Restoration work on part of Newport’s Cliff Walk is taking longer than expected and may keep sections of the state’s most visited tourist attraction closed until mid-July.

The Newport Daily News reports the problem is with a section of the walk near Miramar mansion, midway between Marine Avenue and Ledge Road.

Workers are building a 200-foot-long concrete retaining wall there to prevent erosion from washing soil and rubble onto the walk.

Joseph Godino, an engineer with the state Department of Transportation, says the contractor is working 10 hours, six days a week, but may need up to four weeks longer than anticipated to finish the $5 million project.

While the southern section of the oceanfront walkway has been closed since Superstorm Sandy destroyed parts of it in October, 2012, City Councilwoman Jeanne Napolitano told Eyewitness News the walk from Memorial Boulevard to the Breakers is still open for visitors to enjoy.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s